Canewdon Road – New Build House – Week 10 – 14

Canewdon Road – New Build House – Week 10 – 14

Internal works have started progressing in Week 10 with plasterboard and first fix elec and plumbing, Week 11 saw more slates added to the roof.Insulation was added internally between the rafters.Week 12 and 13 saw the windows fitted and the…

Canewdon Road – New Build House – Week 6

Canewdon Road – New Build House – Week 6

Block work complete at ground floor and all the first floor joists in and the toungue and groove chipboard flooring in…. now the ladders to the first floor

Canewdon Road – New Build House – Week 5

Canewdon Road – New Build House – Week 5

Week 5 – Another busy week with ground floor blockwork and first floor timber joists going in. Externally, we are up to first floor level too with the brick and block.