11 Dane Street – 2

11 Dane Street – 2

Foundations commenced with a mini digger, digging a 450mm wide trench foundation ready for the pot and beam millbank floor.

Garrison Beach Phase 2 week 3

Garrison Beach Phase 2 week 3

Ground cleared, foundations dug, footings in and pot and beam floor has been laid, we are now commencing the brickwork, to match the other houses.

Phase 2 Garrison Beach starts

Phase 2 Garrison Beach starts

We are building an end house to the already completed 5. This is to be a jewel of a three bedroom property.

George street phase 1 is complete

George street phase 1 is complete

We are delighted with the contrast of the bricks, which creates a real statement in the street. The bricks reflect those used in the old Garrison area.

George Street – week 33

George Street – week 33

 Week 33, the roof carcasses are almost complete, windows have started to be installed and the underfloor heating has started, ready for screeding next week.