Canewdon Road – New Build House – Week 10 – 14

week 9a

Week 10Internal works have started progressing in Week 10 with plasterboard and first fix elec and plumbing, Week 11 saw more slates added to the roof.Insulation was added internally between the rafters.Week 12 and 13 saw the windows fitted and the floor screeded.