This week we have completed the render to the outside and started painting it. Installed the staircase and skirtings internally and the floor has gone down in the kitchen/dining area.
We have had Christmas in this period, but the stairs have been fitted and plastering is all but completed on the first floor with architraves and skirtings in.
Internal works have started progressing in Week 10 with plasterboard and first fix elec and plumbing, Week 11 saw more slates added to the roof.Insulation was added internally between the…