Site cleared and ready to commence
Ground cleared, foundations dug, footings in and pot and beam floor has been laid, we are now commencing the brickwork, to match the other houses.
We are building an end house to the already completed 5. This is to be a jewel of a three bedroom property.
with herringbone timber flooring throughout and crittall looking black doors to the rear
We are delighted with the contrast of the bricks, which creates a real statement in the street. The bricks reflect those used in the old Garrison area.
Look what came to visit us! :D
Week 33, the roof carcasses are almost complete, windows have started to be installed and the underfloor heating has started, ready for screeding next week.
Brickwork is progressing up to the second floor gables now
Rinko Falls bricks and Mystique bricks make for a good contrast
The new millbank floor has been laid this week