We have had Christmas in this period, but the stairs have been fitted and plastering is all but completed on the first floor with architraves and skirtings in.
Internal works have started progressing in Week 10 with plasterboard and first fix elec and plumbing, Week 11 saw more slates added to the roof.Insulation was added internally between the…
This week is week commencing 4th November, the weather has been windy. The boys have completed the roof rafters, and have felt and battened the roof ready for tiling. The…
Block work complete at ground floor and all the first floor joists in and the toungue and groove chipboard flooring in.... now the ladders to the first floor
Week 5 - Another busy week with ground floor blockwork and first floor timber joists going in. Externally, we are up to first floor level too with the brick and…